Clayton Armstrong 2011-02-22 GSK Aranda SP - steam&condensat

Esta publicación interactiva se ha creado con FlippingBook, un servicio de streaming de archivos PDF en línea. Sin descargas ni esperas. ¡Solo necesita abrirlo y empezar a leer!

GSK Manufacturing

Aranda de Duero, SPAIN

STEAM AND CONDENSATE ENERGY AUDIT REPORT

PROJECT N° 30275

1

Emission

E. Morin

R. Ivanov

04/02/2011

Item

Description

Established

Checked out

Date

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 2 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

TABLE OF CONTENTS

1 Executive summary ................................................................................................................... 4

2 Steam budget and summary of potential savings ...................................................................... 6

3 Optimisation project n°1: Reduce Boilers Blowdown rate ......................................................... 8

3.1 C URRENT SITUATION .............................................................................................................................. 8

3.2 O PTIMIZATION ....................................................................................................................................... 9

3.3 S AVINGS CALCULATION ........................................................................................................................ 10

3.4 I NVESTMENTS ...................................................................................................................................... 11 4 Optimisation project n°2: Reduce flash steam losses from feedwater tank ............................. 12

4.1 C URRENT SITUATION ............................................................................................................................ 12

4.2 O PTIMIZATION ..................................................................................................................................... 15

4.3 S AVINGS CALCULATION ........................................................................................................................ 16

4.4 I NVESTMENT ........................................................................................................................................ 19 5 Optimisation project n°3: Improve steam ancillaries insulation ............................................... 21

5.1 C URRENT SITUATION ............................................................................................................................ 21

5.2 O PTIMIZATION ..................................................................................................................................... 22

5.3 S AVINGS CALCULATION ........................................................................................................................ 22

5.4 I NVESTMENTS ...................................................................................................................................... 23 6 Optimisation project n°4: Replace failed steam traps.............................................................. 24

6.1 C URRENT SITUATION ............................................................................................................................ 24

6.2 O PTIMIZATION ..................................................................................................................................... 25

6.3 S AVINGS CALCULATION ........................................................................................................................ 25

6.4 I NVESTMENT ........................................................................................................................................ 26 7 Summary of deviations noticed during the audit ...................................................................... 27

7.1 S TEAM GENERATION ............................................................................................................................ 27

7.2 S TEAM DISTRIBUTION ........................................................................................................................... 28

7.3 S TEAM USERS ..................................................................................................................................... 29

7.4 C ONDENSATE RETURN ......................................................................................................................... 32 8 Complete check list of all verifications done during the audit ................................................... 33

9 Recommended complementary studies................................................................................... 35

9.1 A DDITIONAL ENERGY - SAVING OPTIMISATIONS ........................................................................................ 35

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 3 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

9.2 A DDITIONAL OPERATIONAL OPTIMISATIONS ............................................................................................ 36 10 Appendix N°1: Determination of the January 2011 boiler house efficiency .............................. 37

11 Appendix N°2: Steam Pressure Controlled Heat Exchangers at Low Load.............................. 40

11.1 C URRENT SITUATION ............................................................................................................................ 40

11.2 O PTIMIZATION ..................................................................................................................................... 43

11.3 S AVINGS ............................................................................................................................................. 45

11.4 I NVESTMENTS ...................................................................................................................................... 45

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 4 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

Executive summary

1

The energy audit conducted from January 17 th till January 20 th 2011 by Armstrong covers the 4 parts

of the steam loop: boiler house, steam distribution, steam consumption and condensate return.

GSK factory located at Aranda de Duero, in Spain, produces medicines as liquids, aerosols and

tablets.

Steam is mainly used by:

- Coils to produce hot air for fluid bed dryers, coating machines (GLATT) and dehumidifier

(Munters)

- Heat exchangers for sanitization, hot water production, pure steam generation

- Double jackets for reactors heating

Steam is distributed at 7 barg from the new boiler house since one year. The former boiler house is

now stopped. All steam is distributed from the Eagle building to tunnel 2 area and tunnel 1 area.

Steam pressure is then locally reduced to 6, 4 or 2 barg.

Steam is produced by 2 steam generators (Clayton), gas-fired, with a capacity of 3 tons/hr.

The average steam production of the boiler house during the audit is estimated at 0,9 tons/hr. The

steam consumption was low due to the stop of activities in the Eagle Building.

As an indicator, if we use some figures recorded in the old boiler house 2 years ago, your average

steam consumption was about 2 tons/hr.

Our calculations based upon data collected during the audit show a current steam price of 29,5 €

per ton, and an annual steam budget estimated at 133 300 €.

The steam and condensate lines are generally correctly sized.

Insulation of steam ancillaries can be improved.

The steam distribution system is under trapped, especially in front of control valves, resulting in a

serious risk of steam leaks caused by corrosion, erosion and water hammering.

All Condensate that could be recovered is sent back to the boiler house using 3 pumping traps units.

Condensate return ratio was calculated to be 70% during the audit.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 5 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

In order to identify steam leaks, operational problems etc., a steam trap survey was carried out ; in

total 98 traps were tested. The trap survey showed 15% of failed traps (leaking and plugged).

The savings calculated for optimization projects in this report were based upon engineering

assumptions, observations and standard engineering practices.

We estimate the potential energy savings of at least 9% of the estimated steam budget, which

represents a yearly saving of about 377 MWh, 72 tons of CO2 and 11 850 € (see projects 1-3-4).

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 6 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

2 Steam budget and summary of potential savings

The former boiler house (Energy Central 1) was equipped by meters for all energies (gas, water,

steam, condensate) and data were recorded in a global supervision system.

However the new boiler house (Energy Central 2) is not as well equipped. There are only 1 water

meter and 2 gas meters (one for each steam generator) but data is not regularly reported.

Therefore we cannot know your gas consumption for the last 12 months and we cannot calculate

your steam production for the previous year.

Nevertheless, based upon the utility figures during our visit on site in January 2011, we can

estimate:

Boilers steam generation:

• Total yearly steam generation:

3472 MWh (4516 t/year)

• Steam cost:

38.4 €/MWh (29.5 €/t)

• Total yearly steam budget:

133 300 €/year

• Efficiency estimated:

86% (see calculation in appendix n°1)

Basic data considered:

• Gas unit costs :

25 €/MWh hhv

• Gas High Heating Value : 42.1 MJ/Nm³

• Electricity unit costs : 0.064 €/kWh

• Water costs :

o 0.35 €/m³ for city water

o 9000 €/year for Chemicals

o Total = 5 €/m³

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 7 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

Summary of identified energy-saving optimizations and their estimated yearly results:

Note: projects n°1, 3 and 4 should be prioritized as it is simple solutions easy to implement with a

payback time close to 1 year :

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 8 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

3 Optimisation project n°1: Reduce Boilers Blowdown rate

3.1 Current situation

Water impurities and chemicals concentrate (due to evaporation) in a Clayton system as in any

other steam boiler.

To avoid boiler problems, water must be periodically discharged or “blown down” from the boiler to

control the concentrations of suspended and total dissolved solids in the boiler.

The importance of boiler blowdown is often overlooked. If the blowdown rate is too high, you waste

energy (water, fuel, chemicals). If high concentrations are maintained, (too low blowdown) it may

lead to scaling, reduced efficiency, and could lead to water carryover into the steam compromising

the steam quality (wet steam).

Comparing to conventional firetubes steam boilers, Clayton Steam Generators have reduced

blowdown because of two factors:

• Steam Generator is a forced circulation boiler and can tolerate relatively high TDS levels in

the feedwater – as high as 8550 ppm (normal range is 3000-6000 ppm)

• Water that is blowndown is separator trap return water that has been concentrated in the

separator by a factor of, typically, 4 to 5.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 9 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

Because condensate from Clayton separator returns to the feedwater tank, the feedwater will be

concentrated and "cycled up" as in normal boiler water. In other words, the feedwater in the

feedwater tank will have the same composition as the coil water.

Therefore the blowdown rate is calculated with the following formula:

% Blowdown = C make-up water

(C Feedwater – C make-up water )

Where :

C Feed water = the measured TDS concentration in the feedwater tank C make-up water = the measured TDS concentration in the make-up water

- The blowdown system installed on the 2 Clayton in the new boiler house is automatic: the

valve opens every 2 hours during 4 minutes.

According to Nalco monthly water analysis since June 2010, average TDS concentration values are:

- Feed water =50 ppm

- Make up water = 1520 ppm

Therefore your average blowdown rate is 3.4 %

3.2 Optimization

According to the water treatment manual from Clayton, the following water conditions must be

maintained in the feedwater (boiler water) at all operating times:

• Zero hardness

• pH 10.5–11.5 (normal range), maximum of 12.5

• Oxygen free with an excess sulfite residual of 50–100 ppm

• Maximum TDS of 8,550 ppm (normal range 3,000-6,000)

• Maximum dissolved iron of 5 ppm

• Free of suspended solids

• Maximum silica of 120 ppm with the proper OH alkalinity

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 10 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

According to your water analysis, TDS concentration is half of the lowest value recommended by

Clayton. Therefore you could reduce at least by 2 the blowdown rate.

The easiest solution is to change the duration of blowdown valves opening defined in the BMS

system. In agreement with Nalco, you can reduce the blowdown duration to 2 minutes every 2 hours

for example.

Another solution consists in installing a TDS probe on the feedwater line and control the blowdown

valve continuously.

3.3 Savings calculation

Reduce Blowdown rate

Existing

Proposed

Savings

Make-up water TDS

ppm

50,0

50,0

Feedwater TDS

ppm

1520,0

3000,0

Blowdown rate

%

3,40

1,69

1,71

Water savings

Existing

Proposed

Savings

Steam production of the boiler

kg/h

1000,0

1000,0

Blowdown flow

kg/h

34,0

16,9

17,1

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 11 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

Treated Water unit costs

€/m3

5,0

5,0

Water costs

€/yr

1063

530

533

Fuel savings

Existing

Proposed

Savings

Sensible heat Blowdown

kj/kg

721,0

721,0

Sensible heat make up water

kj/kg

50,0

50,0

Sensible heat differential

kj/kg

671,0

671,0

Energy used

kj/h

22823

11373

11450

Boiler efficiency

%

86,0

86,0

Operating hours

hr

6240

6240

Fuel used

MWh/yr

46,0

22,9

23,08

Fuel unit costs

€/MWh

25,0

25,0

Fuel costs

€/year

1150

573

577

CO2 savings

Existing

Proposed

Savings

Energy used

Gj/yr

166 50,6

83

83

CO2 emissions

kg CO2/GJ

50,6

50,6

CO2 produced

t/yr

9,5

4,7

4,7

Total savings

Existing

Existing

Proposed

€/yr

Total costs

2211

1102

1109

Total energy saved by reducing the blowdown rate is estimated at 1110 €/year .

3.4 Investments

No investment is required to change the blowdown frequency on the BMS System.

However we estimate the budget to install a TDS controlled blowdown valve at 9000 €.

Payback time for this optimization would be more than 7 years.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 12 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

4 Optimisation project n°2: Reduce flash steam losses from feedwater

tank

4.1 Current situation

In the new boiler house, 7 barg saturated steam is produced by 2 Clayton generators.

The principle of steam production is the following:

Make-up water and return condensate are blend in the feedwater tank. Feedwater is pumped into

the heating coil, flowing through the spiral single passage section of the coil in a direction opposite

of the combustion gases, where it is rapidly heated to steam temperature. As the fluid leaves the

generator section, it passes through helically wound water wall section, into the separator nozzle in

the steam separator. The centrifugal force in the nozzle separates dry steam from excess water,

which returns to the lower section in the separator. Steam is delivered through the steam discharge

outlet located at the top of the steam separator. The excess water is returned to the feedwater

through the steam trap.

This system allows delivering 99% dry steam within a short time.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 13 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

In order to keep the coil wet at all operating conditions and assure a very good steam quality, a

minimum of 20% excess water is required.

This part of excess water is heated from feedwater tank temperature to saturation (170°C/7 barg)

and evacuated by the steam trap at the separator outlet. This condensate is then sent to the

atmospheric feedwater tank.

Consequently a part of condensate will vaporize from 7 to 0 barg generating 13.5% of flash steam in

the feedwater tank.

Condensate from separator going back to the feedwater tank is useful to maintain the feedwater at

high temperature (90°C minimum required).

We indeed observed that the average temperature in the tank is above 95°C.

Therefore, no extra-steam is needed to maintain the temperature.

However the feedwater tank is still overheated.

Usually, condensate from separator is connected to the bottom of the feedwater tank (under the

water level) using a sparger tube :

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 14 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

This configuration allows maximizing the heat usage and insures a good homogenization of

feedwater temperature in the tank.

However in the new boilerhouse, condensate is connected to the top of the feedwater tank :

Consequently, flash steam generated is not completely condensed and is evacuated through the

vent to the atmosphere.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 15 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

Excess feedwater load

In theory, a minimum of 20% excess water is required for a good operation of the steam generator.

This percentage is set and the feedwater pump has a fixed pumping rate.

It is possible to check if the amount of excess water is in a normal range as it is directly linked to the

amount of condensate evacuated from the steam trap.

The Clayton booklet explains how :

We did measure the opening time for the steam trap when the Clayton was at 25-30% load. I was

about 10 minutes per hour. This value is too high considering the explanation above. We therefore

conclude that the amount of excess water set is too high (about 40%) and so is the amount of flash

steam generated in the feedwater tank.

4.2 Optimization

To prevent from too much flash steam loss at the feedwater tank vent we recommend to:

1. Check with your Clayton distributor if a technician can reduce the amount of excess

water pumped to run properly the generators

2. Move condensate connections from the top to the bottom of the feedwater tank using

a sparger tube : it will help to have an homogeneous feedwater temperature in the

tank

3. Recover condensate heat to preheat combustion air up to 50°C. The solution consists

in installing a coil to heat combustion air using a part of condensate from Clayton

separator.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 16 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

4.3 Savings calculation

Considering our observations and measurement on site, we can estimate the cost of this flash

steam loss:

Fuel savings

Existing

% of revaporisation (7 to 0 barg)

13,5%

Flash steam flow estimated

ton/h

0,066

safety factor

10%

Energy loss

kW

37

operating hours

hr

6240

yearly Energy used

MWh/year

232

boiler efficiency

%

86

Fuel used

MWh/year hhv

300

Fuel unit costs

€/MWh hhv

25

Fuel costs

€/year

7506

CO2 savings

Existing

Energy used

Gj/yr

1081

CO2 emissions

kg CO2/GJ

50,6

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 17 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

CO2 produced

t/yr

55

Water savings

Existing

Flash steam flow estimated

kg/h

0,066

safety factor

10%

Yearly water lost

m³/year

371

Water unit costs

€/m3

5,0

Water costs

€/yr

1853

In conclusion, we estimate the total potential savings at 9360 €/year .

1. Solution 1 : reduce excess feed water rate on the pump

Considering your installation, the Clayton specialist technician will decide how much it is possible to

reduce the amount of excess water pumped.

The following table shows savings calculation if the rate is decreased by 10% :

Fuel savings

Existing

Proposed

Savings

Feewater flow

m³/hr

1,1

1,1

Excess feedwater rate

%

40%

30%

10%

Excess water flow / condensate

m³/hr

0,44

0,33

0,11

% of revaporisation (7 to 0 barg)

13,5%

13,5%

Flash steam flow estimated

ton/h

0,059

0,045

0,015

Energy loss

kW

37

28

9

operating hours

hr

6240

6240

yearly Energy used

MWh/year

232

174

58

boiler efficiency

%

86

86

Fuel used

MWh/year hhv

300

225

75

Fuel unit costs

€/MWh hhv

25

25

Fuel costs

€/year

7506

5629

1876

CO2 savings

Existing

Proposed

Savings

Energy used

Gj/yr

1081

811

270

CO2 emissions

kg CO2/GJ

50,6

50,6

CO2 produced

t/yr

55

41

14

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 18 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

Water savings

Existing

Proposed

Savings

Flash steam flow estimated

kg/h

0,059

0,045

0,015

Yearly water lost

m³/year

371

278

Water unit costs

€/m3

5,0

5,0

Water costs

€/yr

1853

1390

463

The total savings would be 2340 €/year .

2. Solution 2 : Move the condensate connections to the bottom of the tank with a sparger tube

The modification will imply an increase of the feedwater temperature pumped to the generators.

We estimate this increase at 5°C. The efficiency gain on steam production will be about 0.5%.

Boiler efficiency

Existing

Proposed

Savings

Feedwater temperature °C

93,0

98,0

Boiler efficiency

%

86,0

86,5

0,5

Fuel savings

Existing

Proposed

Savings

yearly Energy used

GJ/yr

12499,2

12499

Boiler efficiency

%

86,0

86,5

0,5

Fuel used

MWh/yr hhv

4486

4460

25,93

Fuel unit costs

€/MWh hhv

25,0

25,0

Fuel costs

€/year

112145

111496

648

CO2 savings

Existing

Proposed

Savings

Energy used

Gj/yr

16149

16055

93

CO2 emissions

kg CO2/GJ

50,6

51

CO2 produced

t/yr

817

812

5

Savings are poor (less than 1000 €) because steam production is very low. If the steam demand

increases, savings will follow.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 19 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

3. Solution 3 : preheat combustion air using hot condensate

The preheating of combustion air from ambient to 50°C will lead to an efficiency improvement by

1.5%:

Boiler efficiency

Existing

Proposed

Savings

Intake air temperature (average)

°C

18,0

50,0

Stacks temperature

°C

120,0

120,0

Oxygene content

%

7,0

7,0

Boiler efficiency

%

86,0

87,5

1,5

Fuel savings

Existing

Proposed

Savings

yearly Energy used

GJ/yr

12499,2

12499

Boiler efficiency

%

86,0

87,5

1,5

Fuel used

MWh/yr hhv

4486

4409

76,90

Fuel unit costs

€/MWh hhv

25,0

25,0

Fuel costs

€/year

112145

110222

1922

CO2 savings

Existing

Proposed

Savings

Energy used

Gj/yr

16149

15872

277

CO2 emissions

kg CO2/GJ

50,6

51

CO2 produced

t/yr

817

803

14

4.4 Investment

1. Solution 1 : reduce excess feed water rate on the pump

Budgetary cost for this project is estimated under 1000 €.

Payback time for this optimization is less than 6 Months.

2. Solution 2 : Move the condensate connections to the bottom of the tank with a sparger tube

Budgetary cost for this project is 3000 €.

Payback time for this optimization is about 55 Months.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 20 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

3. Solution 3 : preheat combustion air using hot condenste

Budgetary cost for this project is 13 100€.

Including:

- Air ducts, condensate coil, valves, controls

- Installation work

At level of steam generation seen during the audit, payback time for this optimization is about 82

Months.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 21 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

5 Optimisation project n°3: Improve steam ancillaries insulation

5.1 Current situation

Not only for safety reason, must hot surfaces have effective insulation to

prevent excessive heat loss by radiation. The basic function of insulation

is to retard the flow of unwanted heat transfer. There is more chance of

part of steam to condense during distribution if the pipelines are not

properly insulated.

There is a closely interrelated efficiency between boilers and their

distribution systems. The losses occurred in the distribution systems have

a significant impact on boiler operations. When these losses are minimized, boiler plant efficiency is

improved.

We observed some valves and filters on steam lines which are not insulated in your steam

distribution system.

The following table shows the non-insulated equipments identified during the audit:

Location

Ancillaries length or

DN

Pressure

loss

type

number

(mm)

(barg)

(W)

Boiler house (Eagle)

Back Pressure valves

valve

2

80

7

2106

Eagle building

2nd floor South

valve

2

100

7

2796

Pressure Reducing Station

strainer

1

100

7

1398

Pressure Reducing Station

valve

1

100

4

1137

GLATT 6115

valve

2

32

4

745

2nd Floor North Lavado

valve

1

32

4

373

2nd Floor North Lavado

valve

1

40

4

425

4th floor south

valve

3

40

2

1069

4th floor south

strainer

1

40

2

356

Tunnel 2 aera

1st floor VP37

valve

1

50

6

618

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 22 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

VP43

valve

1

50

6

618

near VP43

strainer

1

50

6

618

VP44

valve

1

40

4

425

to MDU1500

strainer

1

40

4

425

Glatt sala 544 - VP56

valve

2

32

6

869

Glatt sala 544 - VP56

strainer

1

32

6

435

Glatt sala 531 - VP50

valve

1

32

4

373

Glatt sala 535 - VP38

valve

1

32

6

435

Glatt sala 535 - VP38

strainer

1

32

6

435

Tunnel 1 aera

VP16

valve

1

65

3

614

VP4

valve

1

65

3

614

The total radiation loss is calculated at 16882 W.

5.2 Optimization

We recommend installing insulated jackets on all ancillaries located in

steam lines above DN25. These jackets are easy to remove in case of

maintenance operations.

5.3 Savings calculation

SAVINGS Calculation

Total radiation losses

16882 W

Operating hours

6240 h

Annual loss (time corrected)

105,3 MWh/yr

Steam production efficiency

86,0% (lhv)

Annual primary energy loss

122,5 MWh lhv/yr

Annual primary energy loss

135,6 MWh hhv/yr

Fuel cost

25,00 €/MWh

Annual financial loss

3391 €/yr

CO2 emissions

24,7 t CO2/year

Savings calculated are 3400 €/year .

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 23 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

5.4 Investments

Budgetary cost for this project is 6000 €.

Including:

- On site measurement to prepare tailor-made manufacturing of the jackets

- Supply of insulation jackets

- Installation

Payback time for this optimization is less than 21 Months.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 24 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

6 Optimisation project n°4: Replace failed steam traps

6.1 Current situation

A full trap survey was done during our audit. There are 98 steam traps identified and listed on your

steam system drawings. 15 of the installed traps were failing (13 leaking, 2 plugged) and 34 could

not be tested as the units were out of service.

The details of the trap survey and its results are available on SteamStar trap management online

platform.

Here are the access parameters of this trap survey:

Login : beatriz.herrero@gsk.com

Full Name : Beatriz Herrero Gonzalo

Password : B34Tr1ZH3Rr3

Website : www.steamstar.com

Summary of results:

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 25 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

6.2 Optimization

We recommend replacing all steam traps indentified as failed.

Leaking steam traps mean losses of steam. It may also reduce condensate evacuation from process

by creating a back-pressure in the return lines.

Besides, steam in condensate return lines may generate water hammers which can damage your

installation and ancillaries (valves, pressure reducing valve, heat exchangers).

Blocked traps compromise steam quality and cause corrosion and erosion of steam lines and

auxiliaries, resulting in high maintenance costs and increased down time due to system failures.

These traps should be individually evaluated and should be cleaned or replaced by correctly sized

and installed traps.

Some of failed traps were not installed properly (reversed or inclined).

We also noticed a wrong selection for traps n°14-34-35, the pressure differential available is 4.5

barg whereas the steam pressure is 7 barg.

6.3 Savings calculation

Fuel savings

Existing

Steam losses calculated by Steamstar kg/h

50,450

Energy loss

kW

29

operating hours

hr

6240

yearly Energy used

MWh/year

179

boiler efficiency

%

86

Fuel used

MWh/year hhv

231

Fuel unit costs

€/MWh hhv

25

Fuel costs

€/year

5780

CO2 savings

Existing

Energy used

Gj/yr

832

CO2 emissions

kg CO2/GJ

50,6

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 26 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

CO2 produced

t/yr

42

Water savings

Existing

Steam losses

kg/h

50,450

Yearly water lost

m³/year

315

Water unit costs

€/m3

5,0

Water costs

€/yr

1574

Total savings would be 7350 €/year .

6.4 Investment

The budgetary cost for replacing all failing traps is 8000 €.

Including:

- Equipments supply (traps)

- Installation by a mechanical contractor

- Project management

Payback time for replacing all failing traps, including blocked traps, is 13 Months .

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 27 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

7 Summary of deviations noticed during the audit

7.1 Steam generation

Steam is produced by the Energy Central 2 since 2010. This new boiler house is not well monitored

yet.

Gas meters data on the 2 steam generators are not read regularly. As natural gas is also used for

hot water boilers in the Energy Central 1, it is not possible at the moment to know exactly fuel

consumption used to produce steam.

The make-up water meter is reported every day during the daily maintenance (decalcify water).

Some other data are measured and reported to the BMS System:

However some of these probes do not work properly (stacks temperatures, steam temperature) and

only steam pressure is recorded (trends available).

Consequently it is not possible to check on a regular basis the good functioning of the new boiler

house.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 28 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

Gas meters should at least be reported once per month. The best would be to connect meters to the

BMS system (same for water) and record values.

We also recommend you to check if the steam and condensate flowmeters used in the old boiler

house cannot be moved to the new steam production system.

7.2 Steam distribution

Missing condensate drain points

Poor drainage of steam lines will cause accumulation of condensate in the steam distribution

system, thus causing a serious safety hazard for water hammering.

Also on many locations there are no drip legs installed on steam lines in front of control valves. In

some situations there are several meters vertical steam line above a control valve, without a drain

point (especially for Munters feed). When these valves are in a closed position condensate will

accumulate in front of these control valves, and sub-cool. This sub-cooled condensate is aggressive

(low PH) and will cause corrosion of the valves and piping. Also there is a risk for thermo shock and

water hammering. Furthermore accumulated condensate will compromise steam quality and cause

early wear of piping and ancillaries due to erosion.

« Low point »

Steam line size between Eagle and Tunnel 1&2

We have checked the steam line size for the connection between Eagle and Tunnel 1&2.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 29 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

Steam is distributed at 6 barg in a DN65 pipe. As steam velocity should not exceed 30 m/s in the

pipe, the maximum steam flow you could sent safely to Tunnel 1&2 is 1220 kg/hr.

Steam lines DESIGN

Steam pressure

6 Bar(g)

X value

1,00

Line diameter DN

65

Flow

1220 kg/h 30,0 m/s

Steam velocity

max 30,0 m/s

Steam temperature

164,9 °C

specific volume Steam enthalpy Sensible heat

0,27 m3/kg 2763 kJ/kg 697 kJ/kg 2066 kJ/kg

X= 1,00

Latent heat Latent input

X= 1,00

700,1 kW

Currently it is not a problem as your real steam consumption for these areas is lower. However, if for

some reason the steam demand is increased you have to be aware of this limit.

7.3 Steam users

Main steam users are the GLATT systems and the dehumidifier Munters which need hot air.

The factory use 8 GLATT and 9 Munters in the whole site.

-GLATT systems (for coating machines and fluid bed dryers)

Each air handling unit is equipped with 2 or 3 steam coils.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 30 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

The first one is called the “anti-freezing” coil. It is used to pre-heat outside air to 20-30°C.

Often the control valve is a thermostatic one and it is not protected by a drain point upfront.

Therefore this valve may leak rapidly.

Besides, considering the low temperature setting, the steam load in the coil may be low and there

may not be enough pressure to push condensate in the return line. This condition leads to flooded

coils which decrease the heat efficiency and generate slight water hammers. (see appendix n°2 for

detailed explanation)

The second and third steam coils are used to heat the air to 75-85°C. Most of them are equipped

with an automatic ON/OFF valve upfront the control valve. This prevent from steam leaks. However,

we highly recommend installing a steam trap in front of control valves which are installed in “low

point” to prevent from water hammering.

.

The GLATT equipments installed in the Eagle building are also equipped with start-up steam traps.

This steam traps open only with a pressure differential less than 1.5 barg. It allows evacuating

condensate to the sewer when steam pressure is less than back-pressure.

We observed that finally the valves after these steam traps are closed because you lose too much

condensate to the sewer. To avoid this situation you could install a system to push condensate in

the return at any operating condition (see appendix n°2).

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 31 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

-Dehumidifier Munters (for air conditioning)

The Munters system uses a desiccant rotor to remove humidity from outside air.

This desiccant rotor needs to be regenerated using hot air.

The air is heated by a steam coil up to 125°C.

Steam pressure needed is 4.25 barg (indicated in Munters datasheet).

Steam feeding lines are well equipped with control valves and automatic ON/OFF valves.

However there is no drainage point before all valves. Consequently, when the valve is closed,

condensate accumulates in steam line.

- Steam pressure levels

Many pressure reducing stations are installed on steam distribution lines.

However the steam pressure level is not always adapted to the need.

Munters dehumidifiers are designed to use 4.25 barg, but we have seen some equipment fed with 4

barg or even 2 barg steam. Therefore the desiccant regeneration may not be efficient and the

humidity control hazardous.

For GLATT dryers, steam pressure levels are also various:

- WSG120-sala 531, GLATT1350-sala 535 = 3 barg

- GLATT-sala 544 = 4.5 barg

- WSG120-sala 602, Climatiz.Recubrid.- sala 607 = 5 barg

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 32 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

- GLATT 6115-6102-6106, Eagle = 4 barg

Steam pressure levels should be adjusted considering these parameters:

Hot air temperature needed

The lower the steam pressure, the higher the latent heat which is transferred in

the coil

The lower the pressure, the higher the specific volume (attention to be paid to

steam pipe size)

If steam pressure is less than condensate return back-pressure, you may cause

condensate accumulation inside the coil.

-Linea AVAMYS (2 double jacketed reactors)

We observed that there is only one steam trap for the 2 condensate outlets of reactors.

This configuration can only work if the reactors do not run in the same time; otherwise you may have

troubles to evacuate condensate from one of the reactors to the return line.

7.4 Condensate return

Condensate from Tunnel 1 area is collected and sent to Tunnel 2 area with an old pumping-trap.

The condensate header and the pump have been relocated recently and the steam trap on the

motive steam line has not been re-installed. We recommend you to insert the steam trap again to

prevent from rapid erosion and steam leaks on the check valve at the pump steam inlet.

In a general way, there is no high back pressure in condensate return lines as you use 3

atmospheric condensate pumps. In Tunnel 1 and Eagle they are located at the same level or under

steam users. Thus condensate back-pressure is close to 0.

However in tunnel 1, some steam users located on the first floor are “under” the condensate pump

installed on the second floor. Therefore these steam users may be more sensitive to condensate

return back-pressure.

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 33 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

8 Complete check list of all verifications done during the audit

Potential optimisation

Status

Comments

STEAM GENERATION

Steam pressure setting

OK

7 barg is good compromise. 6 barg would certainly

be too low for distribution (lines sizing restrictions)

Feed water temp. to the boilers

OK

93°C measured on the feedwater pump. Clayton

requires a minimum of 90°C

Stack temperature in front of

NA

Not possible to measure on Clayton boilers.

economizer

Stack temperature after economizer

OK

Refer to combustion analysis or temperatures

reported in the BMS system (when repaired)

Combustion air temperature

To be improved

Ambient

Oxygen rate

OK

5-7% depending on the firing rate

Boiler sizing

OK

Boiler blow down rate

To be improved

Could be reduced to fit with Clayton

recommendations

Refer to optimization project n°1

Deaerator pressure

NA

Atmospheric feedwater tank

Feed-water pre-heating

NA

Boiler stand-by time and volatility of

OK

Clayton steam generators have a good response

steam demand

for these conditions

Boiler blow-down recovery

NA

Blowdown is too low at current steam demand to

recover energy within 5 years payback

STEAM AND CONDENSATE AUDIT

Project N°30275

Date: 04/02/2011

GSK MANUFACTURING Aranda, Spain

Page 34 of 45

Established by E. Morin

To the attention of Ms. Beatriz Herrero-Gonzalo

STEAM DISTRIBUTION

External leaks of steam or condensate

OK

No leak has been observed during the audit

from pipes, flanges, etc.

System design, trapping points etc.

To be improved Steam lines have all been interconnected to

distribute steam in both ways (from and to Eagle).

Steam line between Eagle and tunnels 1 and 2 is

undersized for high steam demands.

It misses many trapping points in front of control

valves and in “low points”.

Insulation

To be improved Refer to optimization project n°3

Steam quality

To be improved Steam quality is good at the outlet of the boiler

house but is progressively decreased by the lack of

drip legs in front of steam users

Steam pressure level

To be improved There are many pressure reducing stations. The

pressure level is not always adapted to the steam

usage.

Water hammering

OK

No water hammering has been observed in the

distribution lines

STEAM USERS

Condensate drainage and air venting

OK

from heat exchangers

Steam traps

To be improved 15% failed traps identified

Some traps are wrongly mounted (inclined,

reversed)

CONDENSATE AND FLASH STEAM RECOVERY

Condensate recovered

OK

Sizing of condensate return lines

OK

Flash steam recovery

To be improved Flash steam could be recovered on condensate

receivers. A vent condenser exists in tunnel 2 but is

not used anymore.

Water hammering

OK

Made with FlippingBook Digital Publishing Software