R020932J1, Install Manual

Steam Generator & Fluid Heater Installation Manual

3.7 SCR SKIDS These skids must be shipped with the SCR tank loose. Tank and interconnecting piping must be assembled by the installer. See Supplement I - SCR (pages SI-1 through SI-4) for detailed information. 3.8 HEAD TANK A 10-gallon head tank is required when proper receiver tank elevation is unavailable. A head tank provides the necessary positive coil feed pressure during wet layup. The tank must be installed at least two (2) feet above the steam generator coil inlet connection.

3-8

Sect03_FeedwtrSys_SF_g.fm

07/10/2015

Made with FlippingBook Ebook Creator